• Westfield Ninth-Grade Center

    The new ninth-grade center at Westfield High School will meet the unique academic and social needs of new high school students in a renovated building designed to support a more personalized learning environment.

    The addition of a ninth-grade center will also alleviate crowding in the current high school, creating a safer, more flexible environment for students. Plans for the ninth-grade center include renovating a building north of the high school at 1500 Southridge Road.

  • KEY INFORMATION
    Capacity: 900 Students
    Construction Budget: TBD
    Square Footage: 178,168
    Address:
    1500 Southridge Road

    Architect:  Pfluger
    Contractor:  Satterfield & Pontikes

    Current Status:
    The conteracter and Architectural Team are working on the 2nd GMP Asbestos abatement will start shortly followed by general demolition. Last Updated:July 2019

Project Timeline

  • Planning

     Planning
     Completed

    Done
    Design

     Design
     In progress

    In Progress
    Groundbreaking

     Groundbreaking
     TBD

     
    Crane

     Construction
     TBD

     
    Target

     Target Opening
     Scheduled August 2020

     
    Close-out

     Project Close -Out